| Gas Sweetening Plant- South Pars Phases 6,7& 8 -EPC |
| Client |
POGC |
| Start Date |
Oct. 2009 |
| Progress |
-% |
| Type of Contract |
EPC |
| Location |
Assaluyeh |
| Project Duration/Month |
36 |
| Design Capacity |
3,900 MMSCFD |
| Construction Man Hour |
22,000,000 |
|
|
| back to index |
| Construction of NGL Plant |
| Client |
OIEC |
| Start Date |
Apr. 2009 |
| Progress |
40% |
| Type of Contract |
C |
| Location |
Sirri Island |
| Project Duration/Month |
16 |
| Design Capacity |
140 MCFPD |
| Construction Man Hour |
2,500,000 |
|
|
|
| back to index |
| Sirri-Assaluye onshore 32" pipeline project-EPC |
| Client |
PEDCO |
| Start Date |
Feb. 2009 |
| Progress |
50% |
| Type of Contract |
EPC |
| Location |
Sirri Island |
| Project Duration/Month |
6 |
| Work volume |
17Km |
| Construction Man Hour |
300,000 |
|
|
| back to index |
| Platform Revamping-SouthPars Phase 1-EPC |
| Client |
POGC / Petropars |
| Start Date |
Oct. 2009 |
| Progress |
7% |
| Type of Contract |
EPC |
| Location |
Persian Golf |
| Project Duration/Month |
18 |
| work Volume |
200 MMSCFD |
| Construction Man Hour |
200,000 |
|
|
|
| back to index |
| Tehran Refinery Upgrading-EPC |
| Client |
NIOEC |
| Start Date |
Dec. 2007 |
| Progress |
70% |
| Type of Contract |
EPC |
| Location |
Tehran |
| Project Duration/Month |
32 |
| Design Capacity |
240,000 BPD |
| Construction Man Hour |
3,560,000 |
|
|
| back to index |
| Lavan Refinery Upgrading / License Units-EPC |
| Client |
LAVAN Oil Refinery Co. |
| Start Date |
Dec. 2007 |
| Progress |
47% |
| Type of Contract |
EPC |
| Location |
Lavan Island |
| Project Duration/Month |
30 |
| Design Capacity |
From 30,000 to 60,000 BPD |
| Construction Man Hour |
2,636,000 |
|
|
| back to index |
| Lavan Refinery Upgrading / Utility & Storage Tanks-EPC |
| Client |
LAVAN Oil Refinery Co. |
| Start Date |
Dec. 2007 |
| Progress |
62% |
| Type of Contract |
EPC |
| Location |
Lavan Island |
| Project Duration/Month |
26 |
| Design Capacity |
From 30,000 to 60,000BPD |
| Construction Man Hour |
2,802,200 |
|
|
|
| back to index |
| Saveh Compressor Station-EPC |
| Client |
NIGC/NIGDEC |
| Start Date |
2007 |
| Progress |
72% |
| Type of Contract |
EPC |
| Location |
saveh |
| Project Duration/Month |
24 |
| Design Capacity |
160,000 m³/hr |
| Construction Man Hour |
2,000,000 |
|
|
|
|
| back to index |
| Sirri Island Compressor Station-PC |
| Client |
Petroiran |
| Start Date |
2004 |
| Progress |
99% |
| Type of Contract |
PC |
| Location |
SIRRI ISLAND |
| Project Duration/Month |
21 |
| Design Capacity |
530MMSCFD |
| Construction Man Hour |
2,300,000 |
|
|
|
| back to index |