| Eexcution Of Civil and Mechanical Works Of Flare and Main Pipe Rack,Phase 19 |
| Client |
Petropars |
| Start Date |
Jan.2012 |
| Progress |
3.00% |
| Type of Contract |
C |
| Location |
Kangan |
| Project Duration/Month |
21 |
| Design Capacity |
- |
| Construction Man Hour |
- |
|
|
|
| back to index |
| Designing, Purchasing, Manufacturing, Transportation and Installation of One Wellhead platform(F18) in Foroozan field located in the Persian gulf |
| Client |
IOOC |
| Start Date |
Jan.2012 |
| Progress |
5.00% |
| Type of Contract |
EPC |
| Location |
Persian Golf |
| Project Duration/Month |
20 |
| Design Capacity |
- |
| Construction Man Hour |
- |
|
|
| back to index |
| South Pars Phases 20 & 21 Area C1 |
| Client |
OIEC |
| Start Date |
May.2011 |
| Progress |
15.00% |
| Type of Contract |
C |
| Location |
Assaluyeh |
| Project Duration/Month |
27 |
| Design Capacity |
- |
| Construction Man Hour |
- |
|
| back to index |
| Rehabilitation & Supplying Spare Part for Gas Unit (F6-GE) |
| Client |
Iraq Ministry of Electricity |
| Start Date |
Sep.2011 |
| Progress |
35.00% |
| Type of Contract |
Maintenance |
| Location |
SAMAWA-IRAQ |
| Project Duration/Month |
6 |
| Design Capacity |
37 MW |
| Construction Man Hour |
- |
|
| |
| back to index |
| Construction of NGL Plant |
| Client |
OIEC |
| Start Date |
Apr. 2009 |
| Progress |
98.83% |
| Type of Contract |
C |
| Location |
Sirri Island |
| Project Duration/Month |
16 |
| Design Capacity |
140 MCFPD |
| Construction Man Hour |
2,500,000 |
|
|
|
| back to index |
| Tehran Refinery Upgrading-EPC |
| Client |
NIOEC |
| Start Date |
Dec. 2007 |
| Progress |
96.00% |
| Type of Contract |
EPC |
| Location |
Tehran |
| Project Duration/Month |
32 |
| Design Capacity |
240,000 BPD |
| Construction Man Hour |
3,560,000 |
|
|
| back to index |
| Lavan Refinery Upgrading / License Units-EPC |
| Client |
LAVAN Oil Refinery Co. |
| Start Date |
Dec. 2007 |
| Progress |
83.00% |
| Type of Contract |
EPC |
| Location |
Lavan Island |
| Project Duration/Month |
30 |
| Design Capacity |
From 30,000 to 60,000 BPD |
| Construction Man Hour |
2,636,000 |
|
|
| back to index |
| Lavan Refinery Upgrading / Utility & Storage Tanks-EPC |
| Client |
LAVAN Oil Refinery Co. |
| Start Date |
Dec. 2007 |
| Progress |
89.35% |
| Type of Contract |
EPC |
| Location |
Lavan Island |
| Project Duration/Month |
26 |
| Design Capacity |
From 30,000 to 60,000BPD |
| Construction Man Hour |
2,802,200 |
|
|
|
| back to index |